Made by Simple Capture
Daily log: Maple Ave townhomes, Oct 14
Framing continues on building B. Drywall delivered. One open issue: a missing guardrail at the east stair landing.
| Area | What it saw | Notes |
|---|---|---|
| Weather and crew | Framers (6), electricians (2) | You said: sunny, 62°F |
| Building B | Second-floor wall framing, scissor lift, lumber stack | You estimated framing at units 4 to 6 about 70% done |
| Deliveries | Drywall, 120 sheets | Ticket #48812 read off the slip |
| Inspections | Rough plumbing, unit 2 | Tag reads "Approved 10/13" |
| Issues | East stair landing | Missing guardrail, flagged in your narration at 6:12 |